14 喜欢·259 浏览
单选题

Having decided to rent a flat, we ________ contacting housing agencies in the city.

A
setabout
B
setdown
C
setout
D
setup

题目答案

A

答案解析

【译文】(由于)已决定要租一套公寓,我们开始着手与城里的房屋中介机构接触。

举一反三
单选题

We are all concerned _______ her safety.

A
about
B
in
C
of
D
with

题目答案

A

答案解析

beconcernedabout:关心,担心。句意:我们大家都担心着她的安全。

单选题

I was really anxious about you. You ______ home without a word.

A
mustn’tleave
B
shouldn’thaveleft
C
couldn’thaveleft
D
needn’tleave

题目答案

B

答案解析

虚拟语气用法。句意:我(那时)真的很担心你。你本不应该不留个话就离开家。

单选题

Very few people understood this contract, ______ was very obscure.

A
thelanguage
B
thelanguageofwhich
C
allitsaid
D
whichithadsaid

题目答案

B

答案解析

thelanguageofwhich引导非限定性定语从句,并在定语从句中做主语。句意为:没有几个人懂这份合同,合同的用词含糊不清。

单选题

Sickness often _______ eating too much.

A
asaresultof
B
resultof
C
resultin
D
resultfrom

题目答案

D

答案解析

本题考查result的词组辨析。asaresultof:由于…的结果resultin:导致resultfrom:由…造成,因…而产生

单选题

If you are too ________ of your children, they will never learn to deal with difficulties in life.

A
respective
B
detective
C
protective
D
effective

题目答案

C

答案解析

A个别的、各自的B侦探C保护的、防护的D有效的

单选题

砖墙的水平灰缝厚度()

A
一般为10mm,并不大于12mm
B
一般不小于8mm,并不大于12mm
C
一般大于10mm,并小于12mm
D
一般为8mm,并不大于12mm

题目答案

B

答案解析

暂无解析
单选题

在工程网络计划中,工作m的最迟完成时间为第25天,其持续时间为6天。该工作有三项紧前工作,它们的最迟完成时间为第10天、第12天和第13天,则工作m的总时差为()

A
6
B
9
C
12
D
15

题目答案

A

答案解析

暂无解析